Project Spotlight
Bellevue 600: Bellevue, WA
Sellen Construction is currently undertaking the build of a new, two tower office project in Bellevue, WA. Phase one, a 43 story office tower with underground parking, is underway.
WaterTectonics was brought in to write both the Stormwater Pollution Prevention Plan (SWPP) and Turbidity Monitoring Plan for the project. Sellen also hired WT to handle site permitting including: National Pollutant Discharge Elimination System (NPDES), King County Industrial Waste (KCIW) and City of Bellevue Discharge Authorizations. WT is currently treating the construction site stormwater with a 100 gallon per minute WaveIonics electrocoagulation (EC) system followed by granular activated carbon to meet NPDES/CSWGP and Administrative Order discharge requirements.
Have questions about basic rental packages? Click here or give us a call at: 866-402-2298